Progress Update for Route 66 Improvement Project for Week of Nov. 2

Joplin – A project to make pavement, sidewalk, traffic and safety improvements along Missouri Route 66 (7th Street) in Joplin is underway. Here is an update of the work scheduled for the week of November 2.

Drivers are reminded that access to all businesses along Route 66 (7th Street) will be maintained during hours of operation.

If you have questions or comments about this project, use the comment form found on the project page by clicking here.

Work scheduled:

  • Florida Avenue currently CLOSED on both sides of Route 66 (7th Street) for pavement replacement, installation of new traffic signal infrastructure and to accommodate temporary traffic shift
  • Pavement removal ongoing on south side of Route 66 (7th Street) between Florida Avenue and Ozark Avenue
  • Paving planned for Sunday night, November 8 into Monday morning, November 9
  • Contractor is working with utility companies to complete traffic signal installation at Florida Avenue
  • Contractor is preparing for future closure of St. Louis Avenue pending completion of work at Florida Avenue
  • Contractor is installing temporary signal poles at Murphy Boulevard intersection
  • Liberty Electric relocating light poles on north side of Route 66 (7th Street) between School Avenue and St. Louis Avenue
  • Missouri American Water will be closing crossings at various locations between Schifferdecker Avenue and Main Street
  • Missouri American Water is preparing for closure of Main Street on both sides of Route 66 (7th Street) during nighttime house Monday, November 16 and Monday, November 23
  • Spire relocating gas line on north side of Route 66 (7th Street) between Schifferdecker Avenue and Maiden Avenue
  • City of Joplin crews working between Virginia Avenue and Kentucky Avenue
  • City of Joplin crews preparing for additional work for pipe crossing under Route 66 (7th Street) at Kentucky Avenue
  • City of Joplin crews preparing for sidewalk replacement east of Ozark Avenue
  • AT&T preparing for relocation work at alley way between Pearl Avenue and Wall Avenue
  • Bluebird Fiber working with other contractors for fiber relocation between Murphy Boulevard and Florida Avenue
  • Sparklight working with other contractors for fiber relocation

Traffic Impacts:

  • At least one lane of Route 66 (7th Street) OPEN in both directions
  • Access to all business will be maintained during hours of operation
  • Signs and message boards will alert drivers approaching the work zone
  • No signed detours
  • Check MoDOT’s Traveler Information Map for road closings/traffic impacts

Weather and/or scheduling conflicts could alter the work schedule.

Project Details:

The project will make improvements along the Route 66 (7th Street) corridor in Joplin between Jasper County Route P (Schifferdecker Avenue) and Loop 49 (Range Line Road).

As part of this project, the contractor will rebuild the pavement, bring sidewalks up to Americans with Disabilities Act (ADA) standards, and upgrade and replace several traffic signals along the corridor.

This contract also includes a project to rehabilitate the Oak Street bridge over I-49 in Carthage. That project is likely to start in 2027.

Project Information:

  • Prime Contractor: D&E Plumbing & Heating LLC, Nixa
  • Construction Cost: $61.6 million
  • Contract Completion Date: December 1, 2028

 

 

For more information, call MoDOT in Springfield at 417-895-7600 or visit www.modot.org/southwest. To receive the latest news and text alerts, sign up for e-updates.

Follow MoDOT's Southwest District: Facebook | X | Instagram |YouTube

Take the Challenge! Buckle Up/Phone Down

Legal Disclaimer:

EIN Presswire provides this news content "as is" without warranty of any kind. We do not accept any responsibility or liability for the accuracy, content, images, videos, licenses, completeness, legality, or reliability of the information contained in this article. If you have any complaints or copyright issues related to this article, kindly contact the author above.

Share this page:

Advanced Search Options

Search for:

Search scope:

Type:

Search in:

Date range:

The last

Sort by:

Sign up for:

The Missouri Travel Guide

The daily local news briefing you can trust. Every day. Subscribe now.

By signing up, you agree to our Terms & Conditions.